The build is the short part: 6–12 weeks on our kitchen page. Design, permit review and cabinet lead times come first. They overlap only if someone orders materials during review.
Maksymov Brownstone publishes 4 to 6 months in total for a mid-range kitchen that needs no plan review, and 6 to 12 months for a major or upscale kitchen that goes through Seattle plan review. Those two numbers come from two different pages of ours, so this article uses one rule: the shorter total is for the simpler scope, the longer one for the bigger one. Construction alone runs 2 to 3 weeks for a refresh, 4 to 7 for mid-range, 8 to 14 for a major remodel and 12 to 20 for upscale or custom work (our 2026 kitchen cost guide).
If you remember one thing, remember this: most of the calendar is spent before demolition. A homeowner who plans for “six weeks of construction” and forgets design, permits and cabinet lead times will be wrong by months.
How long does each phase take?
| Phase | Our published duration | Source |
|---|---|---|
| Design, selections and drawings | 4–8 weeks; about 3 weeks of design time per room | Kitchen page, design page |
| Permit review (Seattle) | 2–6 weeks on the kitchen page; the renovation guide gives 2–8 weeks standard and 8–12 weeks for complex projects, plus an intake wait of 2–4 months in busy periods. Compare with the city’s figures below | Kitchen page, renovation guide |
| Ordering and lead times | Custom cabinets 8–14 weeks; we order materials during permit review | Cabinet guide |
| Construction | 2–3 weeks (refresh), 4–7 (mid-range), 8–14 (major), 12–20 (upscale, custom) | Cost guide |
| Final inspections and punch list | 1–2 weeks | Renovation guide |
| Total | 4–6 months for a mid-range kitchen with no plan review; 6–12 months for a major or upscale remodel | Kitchen page, renovation guide |
| Published examples | University District kitchen, 4 weeks; Green Lake Scandinavian kitchen, one month | Case studies |
A “punch list” is the final list of small fixes, such as a door that rubs or a paint touch-up, completed before the last payment. Phases are ranges, so they overlap and will not add up exactly. We do not publish a median, because we have no project records here to support one.

What does the schedule look like for two typical projects?
Adding our published ranges gives a rough picture (our arithmetic, not a promise):
- Mid-range kitchen, no plan review: design 4–8 weeks, permit 2–6, construction 4–7, punch list 1–2. That is 11 to 23 weeks, or about 2.5 to 5 months. Our published total of 4–6 months leaves room for selections, cabinet lead time and scheduling.
- Upscale, custom kitchen with plan review: design 4–8 weeks, permit review 8–12, construction 12–20, punch list 1–2. That is 25 to 42 weeks, or roughly 6 to 10 months. Custom cabinets (8–14 weeks) are ordered during permit review, so they sit inside that window rather than on top of it.
Both fit inside the published totals above. The lesson is where the weeks come from: in the second project, construction is less than half of the calendar.
What do Seattle’s official permit numbers say?
Seattle’s Department of Construction and Inspections (SDCI) tracks permits for “Single Family Addition/Alteration,” which means renovations beyond what a simple permit covers. The city’s goal is 30 days in City control, the time a permit sits with the city rather than waiting on the applicant. The current 75th-percentile figure is 64 days, meaning three-quarters of permits finish within that time. SDCI says the total time an applicant experiences is roughly twice the days in City control, which by our arithmetic is about four months for a project that needs plan review. That is a 75th-percentile figure, not an average. The page shows no data date, and the goals took effect October 1, 2025 (SDCI Construction Permit Performance).
Small projects can use the subject-to-field-inspection permit, a simplified permit that SDCI says needs fewer plan requirements and carries fees based on project value (SDCI). Whether a luxury kitchen qualifies depends on structural, plumbing and electrical changes. SDCI’s own guide to this permit, called Tip 316, lists what it covers (Tip 316). If your scope is borderline, ask the city directly.
For background only: SDCI’s older initial-review guide (updated February 1, 2024) lists 1–2 weeks for simple projects, 2–4 for medium and 4–8 for larger single-family alterations (initial review guide). It predates the current goals, so use it for context, not planning.
Why do custom cabinets add so much time?
Because they are built after the design is final and the measurements are confirmed. Our cabinet guide gives 8–14 weeks for custom, 4–8 for semi-custom and 1–2 for stock. The practical rule: order during permit review, so the wait runs alongside review instead of after it. A design change after the order is the most expensive delay on the list, because the cabinets may need to be rebuilt.
Imported cabinets carry another variable. A 25% Section 232 duty applies now and 50% is scheduled for January 1, 2027, which can affect ordering decisions and contract wording (Federal Register). This is information, not advice.

Can you live at home during a luxury remodel?
Most of our clients stay. Dust is contained, and clients who gut the whole space sometimes leave for the first week of demolition (kitchen page FAQ). Ask how the kitchen function is replaced while the room is closed, and for how many weeks. A temporary setup with a microwave, a small refrigerator and a utility sink handles most households for the construction weeks.
What do clients say about timelines?
“Our kitchen remodel had a rough timeline of being done before Thanksgiving (started Sept 1.), and they absolutely delivered.”
Nicholas A., January 2026, Google review
That client wrote that the project started in early September after an engagement in March. The gap between March and September is the part homeowners forget: design, permit review and ordering came before the first day of construction. Another client, Julia G. (June 2026, Google review), wrote: “Despite changes increasing the project scope (including raising the ceiling height), the kitchen was finished within the promised timeline and the final result was incredible.”
How do you protect your own schedule?
- Decide selections early. A tile change after ordering is a common source of delay.
- Order long-lead items, especially custom cabinets, during permit review.
- Ask for the schedule in phases, and ask which phase is longest.
- Hold changes until a written change order is signed.
- Allow for a contingency in time as well as money.