Houzz puts the national median major remodel at $55,000. Zonda prices a midrange Seattle kitchen at $95,542. Your last bid probably said something else, because each number measures a different thing, and mixing them is how budgets break. These are planning ranges, not a quote for your project.
Seattle’s upscale kitchen remodel costs $188,401 in Zonda’s 2025 Cost vs. Value data (a modeled cost) and recoups 38.7% at resale. Maksymov Brownstone’s own upscale, custom tier runs $150,000 to $300,000+ over 12 to 20 weeks, with Washington sales tax included. The tables below put both side by side, and the sections after them explain why the numbers differ and how to build a budget you can trust.
What does a luxury kitchen remodel cost in Seattle?
Zonda is a housing-data firm. Its annual Cost vs. Value report models what common remodeling projects cost in each metro area and how much of that cost comes back when the home is sold. “Recouped” is the share of the project cost that shows up in resale value. A recouped figure above 100% would mean the project paid for itself; none of the major kitchens do.
| Scope | Seattle job cost | Seattle resale value | Seattle cost recouped | National job cost | National cost recouped |
|---|---|---|---|---|---|
| Minor kitchen, midrange | $32,271 | $38,098 | 118.1% | $28,458 | 112.9% |
| Major kitchen, midrange | $95,542 | $50,762 | 53.1% | $82,793 | 50.9% |
| Major kitchen, upscale | $188,401 | $72,971 | 38.7% | $164,104 | 35.7% |
Source: Zonda Cost vs. Value 2025, Seattle (38th edition, published September 18, 2025). Zonda builds these from real-estate-professional surveys and Verisk XactRemodel cost data. The scopes are standardized, so they are not our definitions and will not match a real project line for line.

What do our own 2026 Seattle ranges look like?
We price real projects, so our ranges are built differently. The ranges below cover a typical 150–250 square foot kitchen and include labor, materials, project management and Washington sales tax. They exclude structural additions (our 2026 kitchen cost guide, published July 23, 2026 and updated September 4, 2026).
| Tier | Our range | Construction time |
|---|---|---|
| Cosmetic refresh: refacing, counters, hardware, paint, no layout change | $18,000–$35,000 | 2–3 weeks |
| Mid-range: new semi-custom cabinets, quartz, appliances, same footprint | $45,000–$85,000 | 4–7 weeks |
| Major: wall removal, relocated plumbing and electrical, new layout | $85,000–$150,000 | 8–14 weeks |
| Upscale, custom: custom cabinetry, slab stone, professional appliances, structural work | $150,000–$300,000+ | 12–20 weeks |
Zonda models one fixed scope. We price what you actually build, so the two will not match.
Other figures we publish: finished work runs $225 to $700 per square foot, a full kitchen permit package costs $800 to $2,500, and a structural report costs $500 to $1,500.
How does a $70,000 mid-range budget break down?
The split below is from our mid-range model. It shows why cabinetry and labor decide most of the price.
| Category | Share | Dollars at $70,000 |
|---|---|---|
| Cabinetry and millwork | 30% | $21,000 |
| Labor | 25% | $17,500 |
| Appliances | 12% | $8,400 |
| Countertops and backsplash | 10% | $7,000 |
| Plumbing and electrical | 8% | $5,600 |
| Flooring | 6% | $4,200 |
| Lighting and hardware | 4% | $2,800 |
| Design, drawings and specifications | 4% | $2,800 |
| Permits and disposal | 1% | $700 |
Three notes on reading it:
- Sales tax. Washington taxes the whole remodeling contract (labor, materials, permits). A $70,000 contract adds $7,385 at 10.55%, Seattle’s combined rate inside city limits, which rose from 10.35% on January 1, 2026. The rate follows the delivery address, so verify it for the Eastside.
- Contingency. We advise setting aside 10–15% for older Seattle homes. On a $70,000 contract that is $7,000 to $10,500. Walls hide things: old wiring, rot behind a sink, a pipe that is not where the drawing says.
- Concentration. Cabinetry and millwork plus labor are 55% of the budget. A decision about cabinets moves the total more than any other single choice.
What happens when you compare the numbers?
Three results from the figures above (our calculation):
- The Seattle upscale kitchen costs about 15% more than the national figure ($188,401 vs. $164,104).
- Going from midrange to upscale in Seattle adds $92,859 of cost and $22,209 of resale value, about 24 cents per extra dollar.
- Luxury is built to live in, not to flip. Plan it as a place you will use for years; the resale math does not carry it. We say so because it is true, and a budget built on a false return fails later.

Why do cost numbers disagree?
Houzz 2026 Kitchen Trends Study (1,780 homeowners, fielded July 2025, self-reported): median major remodel $55,000; $75,000 for kitchens of 250 square feet or more; $46,000 under 250 square feet; 90th percentile $150,000 overall. “Major” means at least all cabinets and appliances were replaced. These are spends people reported, not adjusted for inflation (Houzz PDF).
Census/HUD 2023 American Housing Survey: kitchen remodels reported at about $8,000 per project. That figure includes many small projects such as a new faucet or paint, and the Census infographic labels it the median expenditure for 2021–2023 (Census infographic).
So $8,000, $55,000, $95,542 and $188,401 can all be right. They describe different kitchens in different places and years. When you read a bid, the first question is which kitchen the number describes.
What drives luxury kitchen cost the most?
Cabinet tariffs. A Section 232 duty of 25% has applied to imported kitchen cabinets, vanities and their parts since October 14, 2025. It is scheduled to rise to 50% on January 1, 2027, except for countries that reach a trade agreement with the United States (Federal Register, Proclamation 11000; U.S. Customs and Border Protection guidance). Ask each supplier whether a line is imported and how a duty change is handled in your contract.
Permits. Seattle’s simplified permit, formally the subject-to-field-inspection permit, carries fees based on project value (Seattle Department of Construction and Inspections). Larger scopes go through plan review, which adds time and cost.
Structure. Moving a bearing wall adds an engineer’s report and often a longer permit path. It is the single most common reason a mid-range quote turns into a major one.
How do you read a bid so the number holds?
- Ask which tier the bid describes: refresh, mid-range, major or upscale.
- Ask whether sales tax, permits, disposal and project management are inside the number.
- Ask what is excluded. Structural additions are excluded from our ranges; some bids exclude cabinets or appliances.
- Ask for a contingency in dollars, not a promise that “nothing will come up.”
- Ask when the price becomes itemized. At our firm a preliminary range comes at the first consultation and the itemized estimate comes once the design is final.

What do clients say about cost?
“however with Ihor and his crew the financial estimate was basically exactly what was quoted.”
Nicholas A., January 2026, Google review
“The invoicing process is clear, well-scheduled, and we didn’t have any surprise or phantom costs.”
Michael M., November 2025, Google review
Not every project lands inside the plan, and a fair article says so. Andrew L. (May 2026, Google review) wrote after a whole-house gut renovation: “Although the price went over our planned budget, the results were well worth the cost and wait.” That is why we recommend the contingency above.